(image) Banner

(image) CIRIA logo

home > good practice guidance > case studies > knottingley

Photo: Volker Stevin Ltd

Knottingley Flood Alleviation Scheme

“Ensure at least 60% of aggregates used in Capital works are from secondary/recycled sources.”

Project description

Background
This project involved construction of a new flood embankment to protect 244 properties and creation of a 6hectare wetland habitat.

Waste Minimisation Activity
This project is a good example of a sustainable flood defence scheme, which is enhanced by the use of over 99% recycled materials.

Other than a small amount of asbestos (which was properly disposed of off-site) no other materials were disposed of off-site. The arisings were reused to form a car parking area and a viewing platform.

Materials Targetted

  • Reclaimed clay material to construct the embankment = 25,000 m3
  • Sheet steel piles = 135 tonnes of which 70% were reused

Project Drivers for Waste Minimisation

  • Cost benefits
    - Reused clay material having a favourable price
    - Landfill Tax & other waste disposal costs
  • Client’s high value of waste minimisation and material reuse

Project profile

Location:
Knottingley, England

Project Duration (in relation to the described activities):
April 2004 to September 2004

Client:
Environment Agency

Key Statistics:
25,000m3 reclaimed clay
135 tonnes sheet steel piles – 70% reused

Company Profile

Environment Agency
National Capital Programme Management Service

Client and Project Manager

Project Partners:
Volker Stevin (Principal Contractor)
WS Atkins (Designer)

Project Approach to Waste Minimisation and Sustainable Use of Resources

Design Phase Activities:

Enabling waste minimisation and the use of non-primary materials:
The designers were strongly encouraged to seriously consider non-virgin materials proposed for the sheet piles and clay fill.

Using specifications appropriate to enabling the use of recycled and secondary materials:
The specification for embankment material enabled appropriate recycled materials to be utilised.

Construction Phase Activities:

Enabling waste minimisation and the use of non-primary materials:
Client perception of reuse (where appropriate) was a very positive enabling element.

Using local approaches:
Reclaimed clay sources were investigated at the same time as new during the tendering process.

Company practice and management in supporting waste minimisation and improved approaches to resources use:
A partnering arrangement between the Client and Principal Contractor encouraged a positive culture of waste minimisation and reuse of materials.

Better handling of materials:
Topsoil and subsoil were segregated and reused. Materials from demolished buildings were also segregated and reused.

Good practice in quantifying, costing and recording data on wastes and materials:
KPIs were used to encourage reuse/recycling of materials. The KPI measures were defined as: “Difference in the amount of secondary/recycled materials used in a construction project compared to the total amount of material used in a construction project expressed as a percentage of the total material used”. A target cost contract with pain/gain share was used to encourage cost savings.

Good practice in demolition and deconstruction activities:
Demolition arisings were reused to construct a viewing platform and the car park area.

Lessons Learned, Benefits and Barriers

By maximising both the use of recycled/secondary materials and the reuse of materials on site, costs can be reduced at the same time as minimising potential negative environmental impacts.

sitem

This site is not currently being updated.
All the information on the site was accurate at the time it was last published.