
home > good practice guidance > case studies > knottingley
Knottingley Flood Alleviation Scheme“Ensure at least 60% of aggregates used in Capital works are from secondary/recycled sources.” Project descriptionBackground Waste Minimisation Activity Other than a small amount of asbestos (which was properly disposed of off-site) no other materials were disposed of off-site. The arisings were reused to form a car parking area and a viewing platform. Materials Targetted
Project Drivers for Waste Minimisation
|
Project profileLocation: Project Duration (in relation to the described activities): Client: Key Statistics: Company ProfileEnvironment Agency Client and Project Manager
Project Partners: |
Enabling waste minimisation and the use of non-primary materials:
The designers were strongly encouraged to seriously consider non-virgin materials
proposed for the sheet piles and clay fill.
Using specifications appropriate to enabling the use of recycled and secondary
materials:
The specification for embankment material enabled appropriate recycled materials
to be utilised.
Enabling waste minimisation and the use of non-primary materials:
Client perception of reuse (where appropriate) was a very positive enabling
element.
Using local approaches:
Reclaimed clay sources were investigated at the same time as new during the
tendering process.
Company practice and management in supporting waste minimisation
and improved approaches to resources use:
A partnering arrangement between the Client and Principal Contractor encouraged
a positive culture of waste minimisation and reuse of materials.
Better handling of materials:
Topsoil and subsoil were segregated and reused. Materials from demolished
buildings were also segregated and reused.
Good practice in quantifying, costing and recording data on wastes
and materials:
KPIs were used to encourage reuse/recycling of materials. The KPI measures
were defined as: “Difference in the amount of secondary/recycled materials
used in a construction project compared to the total amount of material used
in a construction project expressed as a percentage of the total material
used”. A target cost contract with pain/gain share was used to encourage
cost savings.
Good practice in demolition and deconstruction activities:
Demolition arisings were reused to construct a viewing platform and the car
park area.
By maximising both the use of recycled/secondary materials and the reuse
of materials on site, costs can be reduced at the same time as minimising
potential negative environmental impacts.
This site is not currently being updated.
All the information on the site was accurate at the time it was last
published.